PRODUCTS
USES
DRIVEWAY
SEALER is a specially formulated coal tar emulsion used as
a protective coating. It is used to preserve asphalt
areas, to seal hairline cracks and to resist the most
adverse weathering action. It is specially recommended
where fuel or oil spillage is likely to occur.
APPLICATION SURFACE PREPARATION
New asphalt areas, hot-mix patches and cold mix patches
must thoroughly cure and consolidate before the DW SEALER
is applied. The surface should be clean, free of dust,
loose stones, grease and other foreign matter. Broom
sweeping or flushing with water under pressure will clean
ordinary surfaces. Accumulation of grease or oil should be
scraped or scoured off using a detergent followed by a
thorough water-rinse. Areas soaked with jet fuel, oil or
petroleum products which resist satisfactory cleaning
should be relaid. Alternately, it can be ground to a depth
of 1.6 3.0 mm from the surface. Areas that are excessively
oxidized (grey in colour) or contain very hard aggregates
like granite and impacted dirt should be primed.
The pavement should present an even surface prior to
coating. In cold-mix surfaces it is particularly
recommended that a small trial patch be applied to be
certain that no softening, cracking or pooling develops.
The pavement must have sufficient stability to carry the
required loading if seal coating is to be effective. After
proper cleaning, the surface should be dampened (no
puddles) in preparation for the application.
APPLICATION METHOD
Prior to application, the material should be stirred
to a uniform, homogeneous consistency. A maximum of 15%
water, by volume, is allowable to give consistency
suitable for application.
With surfaces dampened, the first coat should be poured on
the pavement and spread out evenly and smoothly, using
brushes, squeegees or mechanical applicators.
INTRODUCTION
A
very busy air force runway, a civilian airport taxi way,
an overcrowded apron, an overworked parking area, an
expanse of overused asphalt, all these in time, very short
time, show their use. Thin, invisible hairline cracks
appear which will ultimately put the area out of service.
Unthinkable and may be disastrous if the timing is bad.
The
sealer should be thoroughly worked into surface voids of
the pavement to ensure a continuous protective film. An
excessively heavy coating, "birdbaths" or
"fat spots" are highly undesirable. The second
coat should be applied when the first has satisfactorily
dried (see Drying time). Wherever possible it is
recommended that the second coat be applied at right
angles to the direction of the initial coat. The same
spreading procedure should be followed in putting down
both coats. If one day or more elapses between the first
and second coat, a fine mist or water spray will improve
the ease of applying the second coat.
COVERAGE
Apply at a total application rate of 1 litre/M2
(undiluted) in two coats.
SAND FILLED COATING
For service roadways, rough pavements or where either
increased traction or void filling is desired, apply two
coats at a total application rate of 1-1.5 litres/M2 of
slurry mixture using 0.5 kg/litre of clean sharp 20-40
mesh sand in the first coat and 0.5 litre/M2 for second
coat.
EQUIPMENT
BITUMAT DW SEALER can be applied by brush, squeegee or
mechanical applicators or a combination of these. A push
broom having fine tapioca, nylon or similar fibers is
recommended for open textured pavement surfaces, for
putting down the first coat. Rubber-edged squeegees can
also be utilized as long as they deposit the proper amount
of material.
Mechanical! applicators employing both brushes and
squeegees are suitable as are pressure applicators.
DRYING TIME
Drying time is directly related to the ambient air
temperature, relative humidity and factors such as film
thickness, wind velocity, etc. For best results, it is
recommended that material be applied at temperatures
between 15°C and 27°C.
Light traffic may be permitted when dry. Heavy traffic or
parking of vehicles or aircraft should be avoided until
the coating has thoroughly cured in order to prevent
damage and pickup.
APPLICATION PRECAUTIONS
Work only in good weather. Do not apply in rain or
when frost or rain is forecasted within 24 hours. As
temperature and humidity affect curing
|
Property
|
Result
|
|
Color
|
Black
|
|
Coverage,
Litre/M2
|
1
|
|
Drying
Time, @ 50% RH, 21 0 C.
|
2
Hrs. to touch, firm @ 16 hrs.
|
|
Application
|
10
0 C and temperature rising
|
|
Flammability
|
None
|
|
Specific
Gravity, @ 25 0 C
|
1.2
|
|
Ash
content of solids, % wt
|
35
|
|
Non-Volatile
Percent, % wt
|
47
(minimum)
|
The
information given in this Technical Sheet is to the best
of our knowledge based on laboratory tests and practical
experience. However, as the product is often used under
conditions beyond our control, we cannot guarantee but the
product itself.
|